Rockingham County v. Luten Bridge Co., 35 F.2d 301, 66 A.L.R. 735

Facts

The Luten Bridge Company was awarded a contract by the Rockingham County Board of Commissioners for bridge construction. However, after a commissioner resigned and was replaced, the new board passed resolutions declaring the contract invalid and notifying the bridge company that it would not recognize the contract. Despite this, the bridge company continued construction and later sued the county for payment. The county's defense was based on the claim that the contract was not valid due to the actions of the board.

On January 7, 1924, the board of commissioners of Rockingham county voted to award to plaintiff a contract for the construction of the bridge in controversy.

Issue

Whether the answer filed by certain commissioners admitting liability constituted the answer of the county, and whether the resolutions passed by the board repudiating the contract were valid actions of the county.

Whether the answer filed by Pruitt, Pratt, and McCollum was the answer of the county.

Rule

A county can only be bound by contracts made through its board of commissioners acting as a body in a legally convened meeting. Any actions taken outside of such meetings are not binding on the county.

A county makes its contracts through the agency of its board of commissioners; but to make a contract which shall be binding upon the county the board must act as a body convened in legal session, regular, adjourned, or special.

Analysis

The court determined that the answer filed by the commissioners was not valid as it was not authorized by a legally convened meeting of the board. The resolutions passed by the new board repudiating the contract were deemed valid actions of the county, as they were made by a quorum of the board in a regular meeting. Therefore, the bridge company could not recover for work done after the county had given notice of its intent not to proceed with the contract.

The learned District Judge held that the answer of Pruitt, Pratt, and McCollum was the answer of the county, but we think that this holding was based upon an erroneous view of the law.

Conclusion

The court reversed the lower court's judgment and remanded the case, concluding that the bridge company could not recover the full amount claimed due to the county's prior notice of cancellation.

It follows that there was error in directing a verdict for plaintiff for the full amount of its claim.

Who won?

Rockingham County prevailed in the appeal because the court found that the bridge company continued construction after being notified that the contract was not valid, and thus could not recover for the full amount claimed.

The county now admits the execution and validity of the contract, and the breach on its part, the ultimate question in the case is one as to the measure of plaintiff's recovery.